LogoLogo
Contact SupportRequest Access
  • Home
  • Overview
    • Getting Started
    • Installation
    • Starting a new TimeTable Project
    • Licensing
    • Microsoft Visio
    • TimeTable Ribbon
    • Configure TimeTable Window
  • Importing
    • Supported File Formats
    • Prepping your schedule
    • Importing a Schedule
    • Updates
    • Update Troubleshooting
  • Plan Mode vs Print Mode
  • Timescales
  • Manual Mode
    • Creating Blank Pages
    • What is Manual Mode
    • Adding Manual Tasks
    • Synchronized Copies
    • Step 1: Create a manual page
  • Styles
    • Using the Color Legend with imported metadata
    • Changing Colors
    • Set consistent colors across projects
  • Relationship Links
  • Critical
  • Abbreviations Tool
  • Print to scale
  • Best Practices
    • Multi-Page
    • Limitations
    • Activity Descriptions
  • 🔗Relationships
    • Imported vs Manual
    • Driving vs Non-Driving
  • Label Maker
  • Label Maker
    • Fields
    • Functions
      • List of Functions
  • Tools
    • Abbreviations
    • Label Maker
  • Troubleshooting
    • Extra TimeTable Shapes
Powered by GitBook
On this page
  • Color Coding
  • Critical Path
  • Data Date
  • Excessive links

Was this helpful?

Export as PDF
  1. Importing

Prepping your schedule

How to get the most out of TimeTable, and your schedule

PreviousSupported File FormatsNextImporting a Schedule

Last updated 12 months ago

Was this helpful?

Color Coding

Color coding was one of the many super powers of TimeTable. Most choose to color code according to trade or scope of work. No matter how you decide to color code, putting that data in your single-source of truth

When setting up Activity Codes in Primavera P6, any colors you assign to Activity Code Values will automatically be imported into TimeTable.

You can also set colors in Oracle Primavera Cloud, but they are not included in the XML import as of September 2021. We've reached out to Oracle to change this and will update this article and notify users if this changes.

In Microsoft Project, color coding User Defined Fields (UDFs) is not supported.

Critical Path

Double check your critical path and float values. TimeTable can automatically highlight all activities that meet certain Total Float thresholds.

Some points to remember to assure a good quality:

  1. Make sure all activities (except the first and last) have a predecessor and successor

  2. Use Lags not Leads (Lead is negative lag) in relationships

  3. No hard constraints (i.e. Must Start On), and limit soft constraints (i.e. Must Start on or After)

  4. Keep activity durations, Total Floats, and lags less than 2 months long

  5. Activities with many predecessor and successors should probably be a Milestone

The best way to make sure your project has a realistic Critical Path is by following the .

Data Date

Its always nice to have current information. Do your team a favor and give them a schedule that has been updated recently.

Activities that have started or are completed will show hashing.

Excessive links

TimeTable can hide non-driving relationships and relationships between Activities within the same WBS. However, having an average of more than 5 relationships total for each activity can be a nightmare for managing changes as the project progresses, not to mention it affects performance in Visio.

A good rule of thumb: if you need 6 or more relationships for an Activity, turn it into a Milestone

DCMA 14-point assessment